|
|
|
|
 |
General Dimensions |
|
Imperial |
Metric |
Overall length |
8296 ft |
2528.7 m |
South approach |
10 spans of 168 ft. |
10 spans of 51.2 m |
North approach |
5 spans of 168 ft. |
5 spans of 51.2 m |
Length portal to portal |
5350 ft |
1630.7 m. |
Length tower to tower |
1912 ft. |
582.8 m. |
Cantilever length |
680 ft |
207.3 m. |
Simply supported spans |
350 ft. |
106.7 m. |
Main spans |
[ 2 x 680ft. +350ft.] = 1710 ft. |
[ 2 x 207.3 m. +106.7 m.] = 521.3 m. |
Height of towers |
330 ft. |
100.6 m |
Rail level above high water mark |
158 ft. |
48.2 m. |
Clear navigation headway |
150 ft |
45.7 m. |
Weight of 1710 ft. span |
11571 tons |
11754 tonnes |
Total number of rivets |
6,500,000 nos. weighing 4200 tons |
6,500,000 nos. weighing 4267 tonnes |
|
|
|
Total cost |
£3.2m [foundations £0.8m; abandoned suspension bridge £0.25m.] |
|
|
|
Each double-cantilever tower is founded on 4 piers consisting of 90 ft. [27.4 m.] tall steel caissons filled with concrete up to the topmost 36 ft. [11 m.] which consists of a core of Arbroath stone faced granite. |
|
Quantities of Steel in Main Spans |
|
Queensferry |
Inchgarvie |
Fife |
Total (Tons) |
Central towers (3) |
4815.8 |
7036 |
4815.8 |
16667.6 |
Cantilevers (6) |
1 fixed 1 free |
2 free |
1 fixed 1 free |
|
Bay 1 |
4235.2 |
4312.6 |
4235.2 |
12783.0 |
Bay 2 |
2626.1 |
2658.6 |
2626.1 |
7910.8 |
Bay 3 |
1764.3 |
1724.8 |
1764.3 |
5253.4 |
Bay 4 |
1034.15 |
1009.8 |
1034.15 |
3078.1 |
Bay 5 |
665.9 |
620.2 |
665.9 |
1952.0 |
Bay 6 |
490.1 |
423.6 |
490.2 |
1403.8 |
Central girders (2) |
410.75 |
821.5 |
410.75 |
1643.0 |
Posts and castings |
51.45 |
51.45 |
51.45 |
154.35 |
Ladders |
36.0 |
40.0 |
36.0 |
112.0 |
|
|
|
|
|
Totals (Tons) |
16129.75 |
18698.55 |
16129.75 |
50958.05 |
|
|
|
|
|
| All figures are approximate |
|
Summary of Progress in Erecting the Superstructure |
|
Erected and bolted up |
Riveted |
| Pre 1 January 1886 |
512 tons |
512 tons |
| During 1886 |
8284 tons |
6227 tons |
| During 1887 |
13016 tons |
10536 tons |
| During 1888 |
18767 tons |
18379 tons |
| During 1889 |
9988 tons |
14859 tons |
|
|
|
| Total 1 Jan 1890 |
50567 tons |
50513 tons |
|
| Personnel |
The engineers for the design and execution of the bridge were Sir John Fowler and (Sir) Benjamin Baker assisted by Mr. Allen Stewart, Mr. P.W.Meik - Resident Engineer 1883-6 and Mr. F.E.Cooper – Resident Engineer 1886-90, and others.
Messrs T.E.Harrison and W.H.Barlow approved the design.
The contractors were Sir Thomas Tancred, (Sir) William Arrol, Mr. T.H. Falkiner and Mr. Joseph Phillips. (Sir) William Arrol personally supervised the work, assisted by Mr. Thomas Scott, Manager, Mr. W. Westhofen, who was specially engaged on the works at Inchgarvie; Mr. A.S.Biggart, who was in charge of the drawing offices, shops and yards; and numerous others.
|
Operational Use |
On 21 January 1890 two trains of about 1000 ft. in length entered on to the bridge side by side from the south end. Each train had two locomotives of 72 tons each pulling 50 wagons. The gross weight of each train was 900 tons making a total load of 1800 tons in all. The varying structural displacements under this load were well within the calculated amounts. [See Westhofen W. The Forth Bridge, 1890].
During 1894 the bridge carried 26,451 passengers, 18,777 goods trains and 2678 light engines. The total weight carried was 7,492,833 tons. By 1899 the average weight of a passenger train had risen from 188 to 200 tons and that of goods train from 388 to 400 tons. In 1907 29,675 passenger trains crossed the bridge with a gross weight of 14,674,750 tons.
This usage contrasts with the present day when during 2000 the bridge carried 54,080 passenger and 6240 freight trains with a gross weight of 10,500,000 tons. |
|
 |
Copyright © 2004 Forth Bridges Visitors Centre Trust (a Registered Charity). All rights reserved.

|